Why Do Owners Often Split Construction Into Multiple Work Packages Under An EPCM Model Instead Of Awarding A Single EPC Contract?                                                                                                                                                                                                                                                                                                                                                                                                                                            

Why Do Owners Often Split Construction Into Multiple Work Packages Under An EPCM Model Instead Of Awarding A Single EPC Contract PWCL 2026.png

                                                                                                                                                                                                                                                                                                                                                                                                                                   

We get a lot of questions around EPC Wrap and EPCM contracts; with professionals - investors, developers, and construction contractors - often curious as to the benefits of each; which is the better way of awarding contracts, what the down sides are, and which one is best for complex construction projects?

But, one of the most pressing questions we get asked, and the question we’re answering here, is: “Why Do Owners Often Split Construction Into Multiple Work Packages Under An EPCM Model Instead Of Awarding A Single EPC Contract?”

Why Do Owners Often Split Construction Into Multiple Work Packages Under An EPCM Model Instead Of Awarding A Single EPC Contract?

There’s no one, simple answer to this question, as different investors and organisations prefer to work in different ways, but typically we find that owners often split construction into multiple work pages under an EPCM Model (instead of awarding a single EPC contract) due to the following:

Greater Control And Flexibility

Avoiding The ‘EPC Markup’: Single EPC contracts hinge on one contractor shouldering all of the risk associated with a project. As such, that contractor typically tacks on a contingency markup - often called a ‘wrap-around’ risk fee. However, under an EPCM Model, the owner contracts directly with individual trade contracts and equipment suppliers, consequently eliminating the need for a heavy single-contractor markup.

Direct Management: another reason why an owner might prefer to split contracts under an EPCM Model, rather than a single EPC contract is the benefit of greater control, and direct management; an owner, utilising an EPCM Model, retains direct authority over design changes, scheduling adjustments, and vendor selection, and if something needs to be modified mid-stream, the owner deals with the relevant contractor directly rather than going through the main contractor and their change-order processes.

Risk Distribution Vs. Risk Mitigation

To Spread Or Absorb Risk: A single EPC contract attempts to shift all risk onto one contractor and, if that contractor struggles, the entire project can stall or face catastrophic claims. However, under an EPCM, risk is unbundled and distributed among multiple specialist contractors and suppliers who are best suited to handle their specific scopes.

Increased Administrative Complexity, Decreased Chance Of Single Failure: it’s true that managing multiple contract packages can significantly increase administrative complexity. However, it also prevents the construction project in question from being entirely at the mercy of a single contractor’s financial health, capacity or overall performance.

Schedule and Procurement Speed

Fast-Tracking: An EPCM approach allows owners to tender and award early packages (such as long-lead equipment or site civils) long before the final engineering and design for later phases are completely finished, where a single EPC contract often requires a fully frozen design before a fixed price can be agreed upon, which can add months to the front end of a project.

The Role Of A Project Manager In The EPCM Approach

Splitting construction into multiple work packages under an EPCM model offers significant strategic advantages; eliminating hefty wrap-around risk markups, accelerating early procurement, and protecting your project from single-contractor failure.

However, unbundling those contracts also means the coordination, interface management, and administrative oversight shift directly back onto your team.

To unlock the cost savings and flexibility of an EPCM approach without getting bogged down in day-to-day contractor friction, partnering with an experienced project manager is essential as a dedicated project management team acts as the central nervous system of your build - aligning schedules, managing technical interfaces across multiple work packages, and protecting your budget so your project stays on track from initial procurement through to final handover.