How Soon Is “As Soon As Possible”? Why the UK Biomethane Sector Cannot Afford Further Delays ...
How Soon Is “As Soon As Possible”? Why the UK Biomethane Sector Cannot Afford Further Delays
Given the impending closure of the Green Gas Support Scheme with no indication of a successor, alongside the continuous oversight of biomethane in recent government announcements such as the 2026 Autumn Budget and the Prime Minister’s COP31 speech, the renewable sector is understandably becoming increasingly restless and frustrated, awaiting guidance, support and answers from our MPs to some long-awaited questions.
And, seemingly, it’s not just the renewable sector feeling this way as Josh Newbury, MP for Cannock Chase, raised an important question around biomethane this week, during an appearance in the House Of Commons.
Highlighting the many benefits of biomethane to households, farmers and businesses, whilst simultaneously raising the concern that it’s often left behind in conversation and considered to have already ‘peaked’, MP Josh Newbury asked an incredibly targeted question to Katie White, Minister of State in the Department for Energy Security and Net Zero:
“Will the Minister look at getting the future biomethane framework out the door so we can back this sector to reach its full potential?”
And, although Minister White was unable to provide a timeline or confirm tangible support for the sector, she did acknowledge how important biomethane is to UK energy security and decarbonisation, whilst also stating that - indeed - DESNZ will be doing this “as soon as possible”.
Undoubtedly a masterful response from Minister White and, whilst it’s refreshing to hear such positive words regarding biomethane from someone with influence over policy, it does however raise the question of “how soon is ‘as soon as possible’?”.
It’s now November 2026 and the closing date for applications to GGSS is fast approaching, officially cutting off to Stage 1 applications on 31st March 2028, with a commissioning/Stage 3 deadline of 31st March 2030; giving new biomethane projects just over 16 months to get those Stage 1 applications in.
As we know, it takes time, patience and a lot of work to get an anaerobic digestion plant ready to build, and even longer to build it, ready for commissioning; anywhere, in fact, between 2 and 5 years, depending on complexity.
And, given Stage 1 applications require a biogas plant to have key elements in place such as:
Location and setup (including a grid injection point and equipment description)
Evidence of a signed connection agreement
Evidence of planning permission
Expected maximum initial injection capacity per year, plus the expected start/commissioning date
Which can all take months to acquire, meaning the pressure really is building and, unless you’re already half way through the pre-construction phase as this article goes live, you might not even make the first deadline.
In fact, the lack of an announcement regarding a successor to GGSS is threatening to stunt the UK AD sector altogether, where such uncertainty as to future frameworks and governmental support available are starting to make investors more than a little cautious.
Now, more than ever, biomethane is in desperate need of government support.
Industry professionals, rural MPs and Ministers all agree that biomethane is crucial to UK energy security, long term energy independence, decarbonisation and reindustrialisation; capable of providing tens of thousands of well-paid, skilled and satisfying jobs all across the country.
So, what’s the holdup?